January 31, 2020 | Category: District D | Tagged as: Canal Blvd
Crews from Palmisano Construction continue installation of drainage and sewer lines on northbound Canal between Robert E. Lee Boulevard. and Amethyst Street.
November 22, 2019 | Category: District D | Tagged as: Canal Blvd
The Canal Boulevard Full Depth Reconstruction Project is underway and crews have begun installing new waterlines in the northbound lanes.
October 30, 2019 | Category: District D | Tagged as: Canal Blvd
The Canal Boulevard Full Depth Reconstruction Project began in August 2019, and is expected to continue through summer 2020, weather permitting. Entergy Electric remains onsite performing utility work on southbound Canal Blvd.
September 30, 2019 | Category: District D | Tagged as: Canal Blvd
The Canal Boulevard Full Depth Reconstruction Project began on in August. The northbound side of Canal between Robert E. Lee Blvd. and Amethyst St. is closed to traffic, and the southbound side has been temporarily converted to accommodate two-way traffic.
August 28, 2019 | Category: District D | Tagged as: Canal Blvd
The $4.5M Canal Boulevard Full Depth Reconstruction Project, designed by Integrated Logistical Support, Inc. and awarded to Palmisano Construction, began this month.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at roadwork@nola.gov or by phone at (504) 658-ROAD (7623).