In February, Beverly Construction crews, in collaboration with the Sewerage and Water Board, began preparation work for water line tie-ins on the West End Group A infrastructure improvement project. This month, crews will begin connecting newly installed water lines to the existing water supply on 30thand 20th streets, as well as along Pontchartrain Boulevard. Once complete, the overall project will be approximately 85 percent complete and on target to wrap up in the spring.