Latest News

CONVENTION CENTER BOULEVARD CONSTRUCTION SUBSTANTIALLY COMPLETE

November 19, 2020   |    Category: District B    |   Tagged as: Convention Center Blvd

CONVENTION CENTER BOULEVARD CONSTRUCTION SUBSTANTIALLY COMPLETE

The New Orleans Ernest N. Morial Convention Center has been reconstructing Convention Center Boulevard between Poydras and Henderson streets in the Warehouse District. The construction project, which is now substantially complete, is part of the $557M Convention Center Development District Project that included converting Convention Center Boulevard into a landscaped public park. The contractor is finishing up a few details this month.

FRERET GROUP A APPROACHES 95 PERCENT COMPLETION

November 19, 2020   |    Category: District B    |   Tagged as: Freret

FRERET GROUP A APPROACHES 95 PERCENT COMPLETION

Hard Rock Construction Co. LLC, crews are quickly approaching 95 percent completion on the Freret Group A  project. The completed work represents the original scope of work that began in February 2020. Crews have completed over 90 percent of the asphalt work and 100 percent of the original water line work on this project. While the project is over 90 percent complete, additional work added to the project will extend the overall completion to spring 2021.

MID-CITY GROUP A MAKES STRIDES TOWARD COMPLETION

November 19, 2020   |    Category: District B    |   Tagged as: Mid City

MID-CITY GROUP A MAKES STRIDES TOWARD COMPLETION

Hard Rock Construction crews completed roadway paving and sidewalk work on Conti, S. Salcedo, Dupre and Gayoso streets on the Mid City Group A project. Crews also completed major water line repairs throughout the project. 

FULL DEPTH RECONSTRUCTION WORK BEGINS ON WEBSTER STREET

November 19, 2020   |    Category: District A    |   Tagged as: Audubon

FULL DEPTH RECONSTRUCTION WORK BEGINS ON WEBSTER STREET

Boh Bros crews continue work throughout the  Audubon Group A  project, including full-depth work on the 600 block of Webster Street.  In close collaboration with Sewerage and Water Board of New Orleans crews began the process of chlorinating and testing the new water lines in November. Work has also begun on sewer lines that included closed circuit television (CCTV) monitoring. Crews are expected to wrap this work by mid-December.

BLACK PEARL GROUP B SET TO BEGIN CONSTRUCTION IN DECEMBER 2020

November 19, 2020   |    Category: District A    |   Tagged as: Black Pearl / East Carrollton

BLACK PEARL GROUP B SET TO BEGIN CONSTRUCTION IN DECEMBER 2020

The $5.1M Black Pearl Group B project is set to begin construction in December 2020. This project was designed by Jacobs Engineering Group and will be constructed by Infinity Construction. Click here to view a map of the project scope. 

Displaying results 36-40 (of 53)
 |<  <  2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11  >  >| 
November 2020

Posts by month

November 2023 (1)
October 2023 (0)
April 2023 (1)
October 2022 (1)
August 2022 (2)
July 2022 (1)
December 2021 (1)
November 2021 (57)
October 2021 (1)
September 2021 (2)
August 2021 (3)
July 2021 (2)
June 2021 (56)
May 2021 (3)
April 2021 (5)
March 2021 (64)
February 2021 (55)
January 2021 (57)
December 2020 (55)
November 2020 (53)
October 2020 (52)
September 2020 (44)
August 2020 (40)
July 2020 (38)
June 2020 (38)
May 2020 (34)
April 2020 (30)
March 2020 (29)
February 2020 (30)
January 2020 (23)
November 2019 (24)
October 2019 (21)
September 2019 (22)
August 2019 (18)
July 2019 (18)
June 2019 (23)
May 2019 (23)
April 2019 (23)
March 2019 (23)
February 2019 (27)
January 2019 (27)
December 2018 (26)
November 2018 (26)
October 2018 (26)
September 2018 (27)
August 2018 (27)
July 2018 (26)
June 2018 (29)
May 2018 (21)
April 2018 (20)
March 2018 (18)
February 2018 (20)
January 2018 (20)
November 2017 (17)
October 2017 (15)
September 2017 (14)
August 2017 (13)
July 2017 (18)
June 2017 (16)
May 2017 (14)
April 2017 (15)
March 2017 (17)

Posts by category

Citywide
District A
District B
District C
District D
District E

Posts by project

Algiers
Aubry St
Audubon
Bayou St. John, Fairgrounds, Seventh Ward
Belleville St
Berkeley Dr
bike lanes
Black Pearl
Black Pearl / East Carrollton
Blue & Green Corridors
Bocage
Bourbon
Breakwater Drive
Broad St
Broadmoor
Bullard Ave
Bywater-Marigny
Canal Blvd
Canal St
Central City
Cherokee St
City Park
Community Meeting
Conti
Convention Center Blvd
Curran Blvd
Desire
Desire/Gordon Plaza
East Riverside/Garden District/Irish Channel/St. Thomas
Filmore
Fleur de Lis
Fontainebleau
Fountainebleau
French Quarter
Freret
Gentilly Resilience District
Gentilly Terrace
Gravier St
Green Infrastructure
Hagan Lafitte
Henry Clay
Hollygrove
Hollygrove, Leonidas
Infrastructure Industry Day
Jackson Ave
Joe Brown Park Bridge
Lacour Monique and Eton St.
Lafitte Corridor Greenway
LAKE TERRACE AND OAKS
Lake Vista
Lakeshore
Lakeview
Lakewood
Little Woods
Lower Ninth Ward
Magazine
Magnolia Bridge
Maintenance Improvements
Marconi
Marleyville-Fontainebleau
Maurepas St and Mystery St
Max Pave II
Message from the Mayor
Michoud Blvd
Mid City
Milneburg
Mirabeau Water Garden
Moving New Orleans Bikes
Navarre
New Aurora
New Orleans East
North Claiborne
Oak Park
Octavia Street
Old Spanish Trail
Pilotland
Pines Village
Pittari St.
Plum Orchard / West Lake Forest
Pontchartrain Park
Pontilly
Read Blvd
Resilience
S Galvez
Safe Routes to School
Saratoga Square
St Claude
St Louis Canal
St. Ann
St. Bernard
St. Charles
St. Roch
Streetscape
SWB
Taft Place
Traffic Advisory
Treme-Lafitte
Viavant-Lake Catherine
Village de L’Est
West Bank
West End
Wisner Bridge
Wright Rd
Youth Study Streets


Looking for work?

The City of New Orleans and the Sewerage & Water Board are hiring.

Find jobs with the City

Find jobs with S&WB

Connect to First Source


Contact us

You can contact us directly at ose@nola.gov
or by phone at (504) 658-7623.