Crews completed all sewer line work in October and continued making progress with manhole restorations. Water line work continued, asphalt restoration began on Dwyer Road, and crews proceeded with concrete removal and replacement on Morrison Road. Crews also began asphalt milling and installation of the roadway wearing course in the 4400-4700 blocks of Francis Drive. The approximately $18.2M project was designed by All South Consulting Engineers Inc., and is estimated to be complete in fall 2021 weather permitting. Access the presentation from the public pre-construction meeting here.